Project:
Lowry Centre, Salford Quays, Manchester, UK
Client: Jarvis Newman
Job Started: 16th July 1999
Job Finished: 12th February 2000

M2 Laid and Depth: 2639m2 / 65mm - 95mm & 5mm - 27mm
Products used: Tilcon Truscreed, Ardit Latex